River Route |
Cost (Jan 2000) |
Source |
|
|
|
|
|
Item: |
|
|
|
|
|
|
|
Complete Whitminster Lock |
100,000 |
Bridge=Atkins, guiliotine=quotes |
|
Connection to River |
25,000 |
Atkins=£9k, seems low |
|
River from connection to Latham Aqueduct site |
60,000 |
Atkins |
|
Latham to Fromebridge weir |
140,000 |
Atkins, bridge £50k, river £73k |
|
MOD pipeline |
87,000 |
Atkins + estimates from BPA |
|
Bridge at Fromebridge |
35,000 |
Atkins |
|
Removal of Fromebridge Weir |
100,000 |
Educated guess |
|
Excavation river from Fromebridge to A38 |
150,000 |
Atkins=£101k for new separate channel |
|
Construction of deep channel under A38 |
440,000 |
Halcrow Jan 2000 |
|
Excavation A38 to M5 |
150,000 |
Educated guess |
|
Lower water and gas pipes |
160,000 |
Atkins=£111k without extra depth |
|
Deepen Channel under M5 |
250,000 |
Educated guess |
|
New Lock and Weir (2.7m lock rise) |
200,000 |
Atkins=£250k (thought to be high) |
|
New canal from New Lock to Westfield Bridge |
200,000 |
Atkins=£164k for shorter |
|
|
|
|
|
Total: |
1,997,000 |
|
|
|
|
|
|