| New M5 Bridge Route | Cost (Jan 2000) | Source | |
|---|---|---|---|
| Item: | |||
| Complete Whitminster Lock | 100,000 | Bridge=Atkins, guiliotine=quotes | |
| Connection to River | 25,000 | Atkins=£9k, seems low | |
| River from connection to Latham Aqueduct site | 60,000 | Atkins | |
| River/canal connection and flood gate | 100,000 | Atkins=£55k (flood gate cost too low) | |
| Stonepitts Bridge | 35,000 | Atkins=£29k | |
| Dredging from Stonepitts to A38 | 53,000 | Atkins=£46k | |
| MOD pipeline | 87,000 | Atkins + estimates from BPA | |
| A38 roundabout Bridges | 790,000 | Atkins=£540k+£250k for BT! | |
| New Lock and channel | 480,000 | Atkins=£417k | |
| Farm Access Bridge | 35,000 | Atkins=£30k | |
| Lower water and gas pipes | 92,000 | Atkins=£80k without extra depth | |
| Bridge under M5 (excluding lane rental) | 600,000 | Atkins=£430k slightly south and shorter | |
| M5 lane rental for contraflows | 1,500,000 | Atkins indicative for 4-6 week period | |
| New lock and channel to Westfield Bridge | 426,000 | Atkins=£371k | |
| Farm Access Bridge | 35,000 | Atkins=£30k | |
| Total: | 4,138,000 | ||