New M5 Bridge Route Cost (Jan 2000) Source
Item:
Complete Whitminster Lock 100,000 Bridge=Atkins, guiliotine=quotes
Connection to River 25,000 Atkins=£9k, seems low
River from connection to Latham Aqueduct site 60,000 Atkins
River/canal connection and flood gate 100,000 Atkins=£55k (flood gate cost too low)
Stonepitts Bridge 35,000 Atkins=£29k
Dredging from Stonepitts to A38 53,000 Atkins=£46k
MOD pipeline 87,000 Atkins + estimates from BPA
A38 roundabout Bridges 790,000 Atkins=£540k+£250k for BT!
New Lock and channel 480,000 Atkins=£417k
Farm Access Bridge 35,000 Atkins=£30k
Lower water and gas pipes 92,000 Atkins=£80k without extra depth
Bridge under M5 (excluding lane rental) 600,000 Atkins=£430k slightly south and shorter
M5 lane rental for contraflows 1,500,000 Atkins indicative for 4-6 week period
New lock and channel to Westfield Bridge 426,000 Atkins=£371k
Farm Access Bridge 35,000 Atkins=£30k
Total: 4,138,000