New M5 Bridge Route |
Cost (Jan 2000) |
Source |
|
|
|
|
|
Item: |
|
|
|
|
|
|
|
Complete Whitminster Lock |
100,000 |
Bridge=Atkins, guiliotine=quotes |
|
Connection to River |
25,000 |
Atkins=£9k, seems low |
|
River from connection to Latham Aqueduct site |
60,000 |
Atkins |
|
River/canal connection and flood gate |
100,000 |
Atkins=£55k (flood gate cost too low) |
|
Stonepitts Bridge |
35,000 |
Atkins=£29k |
|
Dredging from Stonepitts to A38 |
53,000 |
Atkins=£46k |
|
MOD pipeline |
87,000 |
Atkins + estimates from BPA |
|
A38 roundabout Bridges |
790,000 |
Atkins=£540k+£250k for BT! |
|
New Lock and channel |
480,000 |
Atkins=£417k |
|
Farm Access Bridge |
35,000 |
Atkins=£30k |
|
Lower water and gas pipes |
92,000 |
Atkins=£80k without extra depth |
|
Bridge under M5 (excluding lane rental) |
600,000 |
Atkins=£430k slightly south and shorter |
|
M5 lane rental for contraflows |
1,500,000 |
Atkins indicative for 4-6 week period |
|
New lock and channel to Westfield Bridge |
426,000 |
Atkins=£371k |
|
Farm Access Bridge |
35,000 |
Atkins=£30k |
|
|
|
|
|
Total: |
4,138,000 |
|
|
|
|
|
|