Digger moves in to excavate the eastern infill
- 5th May 2005
|
The south east corner of Pike Lock where the steps
descend to
the towpath under the bridge with (left to right) the medium pressure
gas main, water main and two telecom ducts running across the tail of
the lock (there is also a low pressure gas main still buried next to
the water main) - 6th May 2005
|
The exposed south abutments of the original 1770s
bridge.
This has survived up to the level where the arch started.
9th May 2005
|
It proved necessary to excavate behind the abutments
right down to the
underlying mudstone almost 5m below ground.
12th May 2005
|
Concrete being poured into the hole excavated behind
the north
abutment on the same day it was excavated.
12th may 2005
|
Excavations on the north west side of the bridge
reveal the
original canal wall and location of the Pike Lock overflow outlet.
10th May 2005
|
Formwork for the eastern deck under construction
19th May 2005
|
View of the bridge from the east side
20th May 2005
|
A photo of the inside of the pike lock overflow culvert
towards the outlet. The last 8ft (2.5m) approx of the culvert was missing
or damaged when the bridge was demolished in 1970 or damaged further by
subsequent water pressure caused by that work.
Photo by Ken Bailey 14th May 2005 - repair work by SW Waterway Recovery
Group and CCT has since been completed.
|
SW Waterway Recovery Group have been working with the
Trust on the Pike Lock overflow culvert. A new retaining wall will be constructed
behind the canal side wall by volunteers.
28th May 2005
|
Reinforcing steel for the eastern deck
26th May 2005
|
The west face with wooden formering for the cross features
removed
9th June 2005
|
Repairs and rebuilding work to the overflow outlet area are complete and
work has started on the retaining wall. 9th June 2005
|
Concrete being poured into the eastern parapet
15th June 2005
|
|
|
|
|
|
|